Question
An organization's accountant is estimating next period's total overhead costs. She performed two regression analyses, one based on direct labour hours and the other based
An organization's accountant is estimating next period's total overhead costs. She performed two regression analyses, one based on direct labour hours and the other based upon machine hours. The results were:
Total overhead = $150,000 + $4 x direct labour hours
Adjusted R-square = 0.65
Total overhead = $130,000 + $5 x machine hours
Adjusted R-square = 0.77
For the next period, the accountant anticipates using 28,000 direct labour hours and 26,000 machine hours. Based upon this information, what is the best estimate for overhead for the next period?
Group of answer choices
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started