Question
An output of 900 units per shift (8.00 hours) is desired for a new processing system. The system requires product to pass through four stations
An output of 900 units per shift (8.00 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 24 seconds. What is the required cycle time for such a system? (Round your answer to the nearest whole number.)
b.How efficient is your system with the cycle time you calculated? (Round your answer to 1 decimal place.)
c.Station 3 changes and now requires 50 seconds to complete. What will need to be done to meet demand (assume only 8.00 hours are available)? What is the efficiency of the new system? (Round your answer to 1 decimal place.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started