1 Approved Answer
An un fav orable labor efficiency variance indicates that: budgeted labor hours exceed actual labor hours the budgeted labor rate exceeds the actual labor rate.
An unfavorable labor efficiency variance indicates that:
budgeted labor hours exceed actual labor hours | ||
the budgeted labor rate exceeds the actual labor rate. | ||
actual labor hours exceed budgeted labor hours | ||
the actual labor rate exceeds the budgeted labor rate |