Anand is developing a neighborhood and installing pools with all the homes. The pool installer takes six days to put in the first pool, and
Anand is developing a neighborhood and installing pools with all the homes. The pool installer takes six days to put in the first pool, and this task has a 90 percent experience curve. How long would it take to install the tenth pool? a. 5.07 days b. 3.55 days c. 4.23 days d. 2.87 days