Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

. Anderson Ltd. manufacture gearboxes for use in cars. At the start of the year, the management of Anderson Ltd. estimated that its costs would

. Anderson Ltd. manufacture gearboxes for use in cars. At the start of the

year, the management of Anderson Ltd. estimated that its costs would be:

This was based on the following:

Direct labour

Direct material

Variable production overhead

Fixed production overhead

Administration overhead

8

50

8

12

5

80 employees

2000 hours worked by each employee

40 000 gearboxes manufactured in the year as budgeted production

200 unit selling price.

You have recently been employed by the company to establish a standard

costing system. At the end of the year you were able to extract the

following information:

labour costs 4.40/hour

32 000 units sold

210/unit selling price

160 000 hours were worked

variable production overheads were 640 000

fixed production overheads were 810 000

administration costs were 350 000

raw material prices were 10% higher than expected

total expenditure on raw material was 3.696 M

there were no opening or closing stocks of raw materials.

(a) You are required to prepare an operating statement for the year, using

a standard absorption costing system.

Calculations should proceed according to the following headings

suffixing A for Adverse and F for Favourable where appropriate.

Resulting quantities required for the statement are then entered in the

Operating Statement for the Year sheet shown on page 6.

(All working must be shown.)

(Budgeted) Costs

Unit cost

Direct labour

Direct materials

Variable overhead

Fixed overhead

Admin. overhead

Total

Selling price

Standard profit (per unit)

Budgeted profit

Sales price variance

Sales quantity variance

Cost Variances

Labour Variances

Standard hours =

Standard cost/hour =

Rate variance =

Standard time =

Actual time =

Time variance =

Efficiency variance =

Material Variances

Material price =

Material usage standard =

actual =

Material usage variance =

Variable overheads

Standard cost =

Actual cost =

Expenditure variance =

Efficiency variance =

Fixed overheads

Expenditure variance =

Volume variance =

Admin overhead (treat as fixed)

Expenditure variance =

Volume variance =

Operating Statement for the Year

000 000

Budgeted Profit

Sales variance price

quantity

Cost variances

Labour rate

efficiency

Material price

usage

Variable expenditure

efficiency

Fixed expenditure

volume

Admin expenditure

volume

Actual Profit

(b) Give reasons/explanations why the variances in (a) above have

occurred for the following:

(i) material price

(ii) labour efficiency

(iii) fixed overhead expenditure.

(c) The accountant suggests that a standard marginal costing system may

be more suitable. He asks you to outline the strengths and

weaknesses of both systems and recommend the most suitable.

(d) The Board of Anderson Ltd. want to adopt ideal standards because

they feel it will encourage harder work. You are asked to produce a

brief report giving your views

Q A answer

The question has multiple parts having multiple subparts. I have answered the parts relating to labor and material variances.

____

Labor Variances:

Labor Cost Variances are calculated as follows:

Formula
Standard Hours (80*2,000) 160,000
Standard Cost/Hour 200*8%*.25 = 4
Rate Variance 64,000 (U) Actual Hours*(Actual rate - Standard Rate) = 160,000*(4.40 - 4)
Standard Time 128,000 (assumed for actual production)
Actual Time 160,000
Time Variance 32,000 (U) Actual Time - Standard Time
Efficiency Variance 128,000 (U) Standard Rate*(Actual Hours - Standard Hours for Actual Production) = 4*(160,000 - 32,000*160,000/40,000) or 32,000*4

____

Notes:

1) F indicates favorable variance and U indicates unfavorable variance.

____

Material Variances:

Material Cost Variances are calculated as follows:

Formula
Material Price Variance 336,000 (U) Actual Material*(Actual Rate - Standard Rate) = 3,696,000/110*(110 - 100)
Material Usage Variance 160,000 (U) Standard Rate*(Actual Material - Standard Material for Actual Production) = 100*(33,600 - 32,000)

____

Notes:

1) F indicates favorable variance and U indicates unfavorable variance.

2) Standard Material Rate = Selling Price*50% = 200*50% = 100

2) Standard material is assumed to be 1 per unit. Therefore, standard material used for actual production would be 32,0000 (32,000*1)

NOTE:i need Question B,C AND D answers.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing An International Approach

Authors: Bahram Soltani

1st Edition

9780273657736

More Books

Students also viewed these Accounting questions