Andrea is a MHIC - licensed contractor for home improvements in Maryland. Derrick calls Andrea about installing a new bathroom in his basement. They sign

Andrea is a MHIC-licensed contractor for home improvements in Maryland. Derrick calls Andrea about installing a new bathroom in his basement. They sign a written agreement that requires a deposit of 13rd of the contract price at contract signing, 13rd at substantial completion, and the balance due on acceptance. A specification is attached that details the scope of work and the location of the bathroom. After Andrea is nearly completed with the project, Derrick calls and tells her that he thinks the bathroom would look better on the second floor. Which, if any, of the following is true?
a) Andrea can only recover in quasi contract against Derrick.
b) Derrick is liable if he refuses to pay the balance owed on the agreement.
c) Andrea is liable if she refuses to move the bathroom to the second floor.
d) Derrick must be subjectively satisfied with Andrea's work as a condition of payment.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions