Angels Inc. fabricates garage doors. Roofs are punched in a roof punching press ( R - Punch ) for 7 minutes per roof, and then
Angels Inc. fabricates garage doors. Roofs are punched in a roof punching press RPunch for minutes per roof, and then are formed in a roof forming press RForm for minutes per roof. Bases are punched in a base punching press BPunch for minutes per base, and then formed in a base forming press BForm for minutes per base. The formed base is welded in a base welding machine Weld for minutes per base. The base and the roof then go to final assembly Assembly which takes minutes per garage door. There is one operator and one machine at each station. The operator and the machine work as a single server.
CapBpng
What is the Theoretical Flow Time? The minimum time required to produce a garage door from start to finish. The potential answers are:
A: minutes.
B: minutes.
C: minutes.
D: minutes.
E: minutes.
What is the capacity of the factory, in terms of garage doors per hour? The potential answers are:
A: units.
B: units.
C: units.
D: units.
E: units.
Where is the bottleneck? The potential answers are:
A: BForm
B: BPunch
C: RForm
D: All
E: Assembly
Suppose we double the capacity of the bottlenecks by adding the same capital and human resources to each bottleneck. What is the new capacity of the system in terms of garage doors per hour? The potential answers are:
A: units.
B: units.
C: units.
D: units.
E: units.
Where is the new bottleneck? The potential answers are:
A: Weld
B: RPunch
C: BPunch
D: As sembly
E: RForm
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started