Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Angels Inc. fabricates garage doors. Roofs are punched in a roof punching press ( R - Punch ) for 7 minutes per roof, and then

Angels Inc. fabricates garage doors. Roofs are punched in a roof punching press (R-Punch) for 7 minutes per roof, and then are formed in a roof forming press (R-Form) for 6 minutes per roof. Bases are punched in a base punching press (B-Punch) for 7 minutes per base, and then formed in a base forming press (B-Form) for 13 minutes per base. The formed base is welded in a base welding machine (Weld) for 5 minutes per base. The base and the roof then go to final assembly (Assembly) which takes 10 minutes per garage door. There is one operator and one machine at each station. The operator and the machine work as a single server.
Cap-B1.png
1. What is the Theoretical Flow Time? (The minimum time required to produce a garage door from start to finish.) The potential answers are:
A: 39 minutes.
B: 46 minutes.
C: 49 minutes.
D: 44 minutes.
E: 35 minutes.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

1st Edition

0749486198, 978-0749486198

More Books

Students also viewed these General Management questions

Question

Identify five strategies to prevent workplace bullying.

Answered: 1 week ago