Angels Inc. is considering bringing the garage fabrication process (which is currently outsourced) in-house. If garage fabrication were brought in-house, the factory would be structured
Angels Inc. is considering bringing the garage fabrication process (which is currently outsourced) in-house. If garage fabrication were brought in-house, the factory would be structured as follows. Roofs are punched in a roof punching press (12 minutes per roof) and then formed in a roof forming press (10 minutes per roof). Bases are punched in a base punching press (12 minutes per base) and then formed in a base forming press (15 minutes per base), and the formed base is welded in a base welding machine (10 minutes per base). The base sub-assembly and the roof then go to final assembly where they are welded together (13 minutes per garage) on an assembly welding machine to complete the garage. Assume one operator at each station.
(a) Draw a process flowchart of the process.
(b) What is the minimum time required to produce a garage (from starting an order to finishing it)?
(c) What is the capacity of the factory in terms of garages per hour?
(d) If you want to increase the capacity, what is the stage that you would put some additional resources?
Step by Step Solution
3.48 Rating (158 Votes )
There are 3 Steps involved in it
Step: 1
Answer 2Roof Time 10 5 15 Punching press 10 minutes Forming press 5 minutes total 15 minutes Base ti...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started