Annabello Co. which is a publicly traded company started to build a 20-story Condo building in May 2018. The project will take 5 years to

Annabello Co. which is a publicly traded company started to build a 20-story Condo building in May 2018. The project will take 5 years to finish, and the total contract price is $80,000,000. The following table provides information about the cost and revenue of the contract

20182019202020212022

Costs incurred during the year

$15,400,000$14,000,000$29,000,000$10,000,000$4,000,000

Estimated costs to complete the project

45,000,00038,5000,00022,000,0008,000,0000

Billings

15,000,00016,000,00020,000,00019,000,00010,000,000

A) Assume the company uses the percentage of completion method based on input, calculate and record the revenue and profit for each year.

B) Determine how this contract will be presented in the balance sheets of 2019

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Percentage of Completion Method Total Cost Incurred Till of Completi Total ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Paul M. Fischer, William J. Tayler, Rita H. Cheng

11th edition

538480289, 978-0538480284

More Books

Students also viewed these Accounting questions