answer all questions shows jobs arrived to be processed. Determine the jobs schedule Due Date (days) 30 50 25 80 60 Table in the following
answer all questions
shows jobs arrived to be processed. Determine the jobs schedule Due Date (days) 30 50 25 80 60 Table in the following sequence rules: (1) First Come, First-Served (FCFS) (ii) Shortest Processing Time (SPT) (iii)Earliest Due Date (EDD) (iv) Slack Time Remaining (STR) (v) Critical Ratio (CR) Job A B C D E Table Processing Time (days) 20 30 10 16 18Step by Step Solution