Question
Answer both problems and show all work for a quick thumbs up 3.6. The Acme Widget Company makes widgets in two models, and the bottleneck
Answer both problems and show all work for a quick thumbs up 3.6. The Acme Widget Company makes widgets in two models, and the bottleneck operation is in work center 10. Following is the resource bill (in hours per part).
Hours per Part | ||
Work Center | Model A | Model B |
10 | 2.4 | 3.5 |
The master production schedule for the next 5 weeks is
Week | 1 | 2 | 3 | 4 | 5 |
Model A | 70 | 50 | 50 | 60 | 48 |
Model B | 20 | 40 | 55 | 30 | 45 |
Using the resource bill and the master production schedule, calculate the number of hours required in work center 10 for each of the 5 weeks. Use the following table to record the required capacity on the work center.
Week | 1 | 2 | 3 | 4 | 5 |
Model A | |||||
Model B | |||||
Total Hours |
Answer. The total hours required are as follows: week 1, 238; week 2, 269; week 3, 313; week 4, 249; and week 5, 273
If the available capacity at work station 10 is 260 hours per week, suggest possible ways of meeting the demand in week 3.
3.8. Given the following data, calculate how many units are available to promise. There are 5 units on hand.
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Customer Orders | 21 | 17 | 8 | 3 | ||
MPS | 30 | 30 | 30 | |||
ATP |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started