answer it asap this question is related to project management answer it faslty 29) Use the above network diagram and activity lengths in the nodes

answer it asap
image text in transcribed
this question is related to project management answer it faslty
image text in transcribed
29) Use the above network diagram and activity lengths in the nodes to determine the late start time for activity F. (1mark) A) 21 B) 24 C) 26 D) 23 30) Use the above network diagram and activity lengths in the nodes to determine the early finish time for activity G. (1mark) A) 26 B) 25 C) 24 D) 23 31) Use the above network diagram and activity lengths in the nodes to determine the late finish time for activity C. (1mark) A) 12 B) 13 C) 14 D) 15 32) The most common type of logical sequencing between tasks is referred to as the: (1mark) A) Finish to start relationship. B) Finish to finish relationship. C) Start to start relationship. D) Start to finish relationship. 33) The process of accelerating a project is referred to as: (1mark) A) Streamlining. B) Expediting. C) Rushing. D) Crashine- 34) One reason for crashing a project is: (1mark) A) The project has slipped behind schedule. B) That the initial schedule may be too pessimistic. C) Market needs change and the project is not in demand anymore. D) There are no repercussions for delivering the project late. 29) Use the above network diagram and activity lengths in the nodes to determine the late start time for activity F. (1mark) A) 21 B) 24 C) 26 D) 23 30) Use the above network diagram and activity lengths in the nodes to determine the early finish time for activity G. (1mark) A) 26 B) 25 C) 24 D) 23 31) Use the above network diagram and activity lengths in the nodes to determine the late finish time for activity C. (1mark) A) 12 B) 13 C) 14 D) 15 32) The most common type of logical sequencing between tasks is referred to as the: (1mark) A) Finish to start relationship. B) Finish to finish relationship. C) Start to start relationship. D) Start to finish relationship. 33) The process of accelerating a project is referred to as: (1mark) A) Streamlining. B) Expediting. C) Rushing. D) Crashing. 34) One reason for crashing a project is: (1mark) A) The project has slipped behind schedule. 8) That the initial schedule may be too pessimistic. C) Market needs change and the project is not in demand anymore. D) There are no repercussions for delivering the project late

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions