Question
Answer the following MCq's with reference to MS project Each week your boss hands you an Excel spreadsheet that contains a list of tasks and
Answer the following MCq's with reference to MS project
Each week your boss hands you an Excel spreadsheet that contains a list of tasks and their estimated durations. He is not familiar with how MS Project works and isn't interested in learning about it. Your team on the other had has expertise in using Project and wants to import the tasks into a MS Project plan. What is the easiest way for you to deal with this situation, given that you have to look after it every week.
Copy the Task List and Duration columns from Excel into Project. | |
Use the Import Wizard to make a data map, so that you can just import the Excel file into Project. | |
Retype the task list and durations into MS Project. | |
Each week, print a copy of the task list and durations and give it to your team. |
The Resource Allocation view is a combination view that is comprised of two which two views.
Resource Usage view in top window; Resource Form view in the bottom window | |
Gantt Chart in top window; Task Form in the bottom window | |
Resource Usage view in top window; Levelling Gantt in bottom window | |
Resource Sheet in the top window; Resource Allocation view in the bottom window |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started