Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Answer the following questions with regard to the AIA A201 - General Conditions of the Contract for Construction , a required reading item for Module
Answer the following questions with regard to the AIA A201™ - General Conditions of the Contract for Construction, a required reading item for Module 4:
- a). An abandoned well was found in the area of a proposed footing, and the well cap was clearly visible. The contractor claimed additional costs for structural fill. Should the architect approve his claim?
- b). Does the owner have the right to subcontract out portions of the work directly?
- c). The building official pointed out that the lack of fire alarms in the project violated local building codes. The owner went after the electrical contractor for negligence in reviewing the drawings. Should the electrical contractor be responsible for the delay and additional cost in fixing this problem?
- d). How can the contractor check on the owner’s financial strength?
- e). In the contract, the stipulated allowance for the carpet is $10,000. The contractor spent $9,500 (delivery and tax included) on purchasing the carpet chosen by the owner and $1,000 on installation. This project specifies 10% for overhead and profit markup for change orders. How much adjustment is the contractor entitled to for this allowance item?
- f). Why is it important to identify the owner’s representative in writing?
- g). The contractor encountered materially different site conditions during excavation. In order to make a claim for additional costs, when does he have to file the claim?
- h). Does the owner have the right to reject a general contractor’s (GC’s) subcontractor who is reasonably capable of performing the work?
- i). What insurance is the contractor responsible to purchase and maintain? What insurance is the owner’s responsibility?
- j). The contractor backfilled the foundation before the architect got a chance to inspect the work, though he had been notified to wait until the architect’s visit. When the architect arrived on site, he ordered the contractor to dig out the backfill at many places. No defective work was found. Could the contractor claim the cost of removing and repairing the backfill?
- k). The architect didn’t request to inspect the plumbing rough-in. However, after the drywall had been installed, he requested to check several critical piping connections which had
- already been covered. Who should bear the cost of removing, repairing and replacing the drywall?
- l). What if the plumbing work was found to comply with the contract documents?
- m). What if some of the connections were found to be defective?
- n). What is the cost to the owner to terminate a project for “convenience”?
Step by Step Solution
★★★★★
3.47 Rating (163 Votes )
There are 3 Steps involved in it
Step: 1
K As it is mentioned that the contractor was notified to wait till t...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started