Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs.
Question:
Antuan Company set the following standard costs for one unit of its product.
Direct materials (4.0 Ibs. @ $6.00 per Ib.)$24.00Direct labor (1.7 hrs. @ $14.00 per hr.)23.80Overhead (1.7 hrs. @ $18.50 per hr.)31.45Total standard cost$79.25
The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the 75% capacity level.
Overhead Budget (75% Capacity)Variable overhead costsIndirect materials$15,000Indirect labor75,000Power15,000
Repairs and maintenance30,000Total variable overhead costs$135,000Fixed overhead costsDepreciation?Building23,000Depreciation?Machinery71,000Taxes and insurance16,000Supervision226,750Total fixed overhead costs336,750Total overhead costs$471,750
The company incurred the following actual costs when it operated at 75% of capacity in October.
Direct materials (61,500 Ibs. @ $6.20 per lb.)$381,300Direct labor (20,000 hrs. @ $14.40 per hr.)288,000Overhead costsIndirect materials$41,950Indirect labor176,400Power17,250Repairs and maintenance34,500Depreciation?Building23,000Depreciation?Machinery95,850Taxes and insurance14,400Supervision226,750630,100Total costs$1,299,400
rev: 03_28_2018_QC_CS-122864
4.Compute the direct labor cost variance, including its rate and efficiency variances.
AH = Actual Hours
SH = Standard Hours
AR = Actual Rate
SR = Standard Rate
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/06/66773d8c4153d_57266773d8c2f69c.jpg)