Any approved budget increase should be: 1. Added to the project's cost baseline 2. Added to the project contingency fund and only used as a
Any approved budget increase should be:
1. Added to the project's cost baseline
2. Added to the project contingency fund and only used as a last resort
3. Added to the project's lessons learned
4. Offset by budget take-aways from direct cost accounts