APPENDIX II ACCOUNTING ISSUES YEAR ENDED DECEMBER 3 1 , 2 0 2 1 New International Terminal During the year, PA constructed a new terminal

APPENDIX II
ACCOUNTING ISSUES YEAR ENDED DECEMBER 31,2021
New International Terminal
During the year, PA constructed a new terminal to allow the airport to offer flights to international destinations. As a result of these activities, PA accounting staff has capitalized $46,907,000 in attributable costs, as outlined below.
\table[[Cost Component,Amount,Description],[Land preparation,,\table[[Preparing the land upon which the terminal would be],[built,such that it was within code for airport],[operations, fuel],[storage, etc.]]],[Professional fees,$600,000,Architectural and engineering fees],[\table[[Advertising and],[promotion activities]],$,78,000,\table[[Advertising in local newspapers to educate the public],[onhow their airport improvement fees were being spent]]],[\table[[Staff time for],[working on the],[project]],$,383,000,\table[[Employee salaries and benefits attributable to the],[property, allocated using timesheets. Includes],[$100,000 for the fair value of share-based payments],[with a three-year vesting period]]],[Interest costs,$,140,000,\table[[Interest costs related to borrowings used to help],[finance operations as a result of the strain on cash flow],[caused byconstruction of the terminal]]],[Building costs,$45,328,000,\table[[Costs of materials and construction labour to build],[theterminal]]],[Training costs,28,000,\table[[Salary and benefits of the terminal manager for time],[spenttraining employees on new systems]]]]
On November 1,2021, the terminal was substantially complete and PA began servicing international routes.
Events after December 31,2021
On January 21,2022,10 jetbridges for the new international terminal were lost in a fire. The fire was due to faulty electrical work. The cost of reconstructing these jetbridges, minus what the insurance company will cover, will be $8.4 million.
At year-end, we accrued $250,000 in architecture fees for the new international terminal; however, due to out-of-scope billings, the architecture firm has since submitted an invoice totalling $400,000.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Global Financial Accounting And Reporting Principles And Analysis

Authors: Peter J. Walton, Walter Aerts

3rd Edition

1408062860, 9781408062869

More Books

Students also viewed these Accounting questions