Application 5.1 ONeill Enterprises manufactures three unique products (A, B, C) that are fabricated and assembled in four different workstations (W, X, Y, Z) using

image text in transcribed

Application 5.1

ONeill Enterprises manufactures three unique products (A, B, C) that are fabricated and assembled in four different workstations (W, X, Y, Z) using a small batch process. Each of the products visits every one of the four workstations, though not necessarily in the same order. Batch setup times are negligible. ONeill can make and sell up to the limit of its demand per week, and there are no penalties for not being able to meet all the demand. Each workstation is staffed by a worker dedicated to work on that workstation alone, and is paid $12 per hour. Variable overhead costs are $8000/week. The plant operates one 8-hour shift per day, or 40 hours/week.

Which of the four workstations W, X, Y, or Z has the highest total workload, and thus serves as the bottleneck for ONeill Enterprises?

Work-station

Load from product A

Load from product B

Load from product C

Total

W

X

Y

Z

Application 5.2

Traditional Method:

1.Calculate contribution margin per unit of each product

Product A

Product B

Product C

Order of production:

2. Allocate resources to production

Work -station

Minutes @ Start

After Making ___________

After Making ____________

After Making ____________

W

2400

X

2400

Y

2400

Z

2400

3. Compute profit for the product mix

Revenue:

Materials:

Labor:

Overhead:

Profit:

Bottleneck method:

1.Calculate contribution margin per unit per minute at bottleneck of each product

Product A

Product B

Product C

Order of production:

2. Allocate resources to production

Work -station

Minutes @ Start

After Making ___________

After Making ____________

After Making ____________

W

2400

X

2400

Y

2400

Z

2400

3. Compute profit for the product mix

Revenue:

Materials:

Labor:

Overhead:

Profit:

Product A Finish with Product: A at workstation D:65 units/wk Step 1 at workstation Step 2 at workstation Step 3 at workstation $7 step 4 P: $90/unit (10 min) (15 min) (9 min) Raw materials min 6 Purchased part Product B Step 1 at workstation Step 2 at workstation Step 3 at workstation Finish with step 4 $9 Product: B at workstation P: $85/unit D:70 units/wk (12 min) (10 min) (10 min) Raw materials min $5 Purchased part Product C Finish with Product: C Step 1 at workstation Step 2 at workstation Step 3 at workstation step 4 10 P: $80/unit at workstation fD: 80 units/wk (5 min) (10 min) (12 min) min Raw materials Purchased part

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Capital Budgeting

Authors: Pamela P. Peterson

1st Edition

0471218332, 9780471218333

More Books

Students also viewed these Finance questions

Question

Change can be created, but never managed. Discuss.

Answered: 1 week ago

Question

Identify the major phases of the training and HRD process

Answered: 1 week ago