Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,580 to date. During October, Jobs 878, 879, and 880 were started. Data on costs added during October for all jobs are as follows: Job 877 Job 878 Job 879 Job 880 Direct materials $14,450 $6,030 $3,530 $1,800 Direct labor 15,800 8,200 2,000 2,000 Overhead is applied to production at the rate of 70% of direct labor cost Job 877 was completed on October 28, and the client was billed at cost plus 50%. All other jobs remained in process. Required: 1. Prepare a brief job-order cost sheet showing the October 1 balances of all four fobs, plus the direct materials and direct fabor costs during October. There is no need to calculate applied overhead at this point or to total the costs, All amount celfs must have an entry; enter zeros as needed. Gorman Company Job-Order Cost Sheets For the Month of October Job 877 Job 878 Job 879 Job 880 Beginning balance materials Required: 1. Prepare a brief job-order cost sheet showing the October 1 balances of all four jobs, plus the direct materials and direct labor costs during October. There is no need to calculate applied overhead at this point or to total the costs. All amount cells must have an entry, enter zeros as needed. Gorman Company Job-Order Cost Sheets For the Month of October Job 877 Job 878 Job 879 Job 880 Beginning balance Direct materials Direct labor 89 2. Calculate the overhead applied to each job during October. The overhead applied to Job 877 is The overhead applied to Job 878 is s The overhead applied to Job 879 iss The overhead applied to Job 880 is 3. Calculate the balance in Work in Process on October 31. The balance in Work in Process for Job 878 is s Beginning balance Direct materials Direct labor 2. Calculate the overhead applied to each job during October. The overhead applied to Job 877 is $ The overhead applied to Job 878 is $ The overhead applied to Job 879 is $ The overhead applied to Job 880 is s 3. Calculate the balance in Work in Process on October 31. The balance in Work in Process for Job 878 is $ The balance in Work in Process for Job 879 is s The balance in Work in Process for Job 880 is s The total balance in Work in Process is $ 4. What is the price of Job 877? The price of Job 877 is $