Applying Overhead to Jobs, Costing Jobs Gorman Company builds internal conveyor equipment to client specifications. On October 1 , Job 8 7 7 was in

Applying Overhead to Jobs, Costing Jobs
Gorman Company builds internal conveyor equipment to client specifications. On October 1, Job 877 was in process with a cost of $18,710 to date.
During October, Jobs 878,879, and 880 were started. Data on costs added during October for all jobs are as follows:
Job 877 Job 878 Job 879 Job 880
Direct materials $14,420 $6,030 $3,530 $1,780
Direct labor 15,2008,6002,2002,500
Overhead is applied to production at the rate of 70% of direct labor cost. Job 877 was completed on October 28, and the client was billed at cost plus 50%. All other jobs remained in process.
Required:
Question Content Area
1. Prepare a brief job-order cost sheet showing the October 1 balances of all four jobs, plus the direct materials and direct labor costs during October. There is no need to calculate applied overhead at this point or to total the costs. All amount cells must have an entry; enter zeros as needed.
Gorman Company
Job-Order Cost Sheets
For the Month of October
Job 877 Job 878 Job 879 Job 880
Beginning balance $fill in the blank 2c3e7a000043fb9_1
$fill in the blank 2c3e7a000043fb9_2
$fill in the blank 2c3e7a000043fb9_3
$fill in the blank 2c3e7a000043fb9_4
Direct materials fill in the blank 2c3e7a000043fb9_5
fill in the blank 2c3e7a000043fb9_6
fill in the blank 2c3e7a000043fb9_7
fill in the blank 2c3e7a000043fb9_8
Direct labor fill in the blank 2c3e7a000043fb9_9
fill in the blank 2c3e7a000043fb9_10
fill in the blank 2c3e7a000043fb9_11
fill in the blank 2c3e7a000043fb9_12
Question Content Area
2. Calculate the overhead applied to each job during October.
The overhead applied to Job 877 is $fill in the blank 89308c04305200c_1
.
The overhead applied to Job 878 is $fill in the blank 89308c04305200c_2
.
The overhead applied to Job 879 is $fill in the blank 89308c04305200c_3
.
The overhead applied to Job 880 is $fill in the blank 89308c04305200c_4
.
3. Calculate the balance in Work in Process on October 31.
The balance in Work in Process for Job 878 is $fill in the blank 89308c04305200c_5
.
The balance in Work in Process for Job 879 is $fill in the blank 89308c04305200c_6
.
The balance in Work in Process for Job 880 is $fill in the blank 89308c04305200c_7
.
The total balance in Work in Process is $fill in the blank 89308c04305200c_8
.
4. What is the price of Job 877?
The price of Job 877 is $fill in the blank 89308c04305200c_9
.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Nmap Network Exploration And Security Auditing Cookbook

Authors: Paulino Calderon

2nd Revised Edition

1786467453, 978-1786467454

More Books

Students also viewed these Accounting questions

Question

Define induction and what are its objectives ?

Answered: 1 week ago

Question

Discuss the techniques of job analysis.

Answered: 1 week ago

Question

How do we do subnetting in IPv6?Explain with a suitable example.

Answered: 1 week ago

Question

Explain the guideline for job description.

Answered: 1 week ago

Question

What is job description ? State the uses of job description.

Answered: 1 week ago