Applying the six steps of the PERT and CPM methods of planning analysis - Define the project Develop relationships and order of activities Draw the
Applying the six steps of the PERT and CPM methods of planning analysis -
- Define the project
- Develop relationships and order of activities
- Draw the network connection of activities
- Assign time & cost estimates
- Compute the longest time (critical time) path
- Use the network to plan, schedule, monitor, and control the project