Question
Aramco company was awarded a $63 million contract to build a bridge. The estimated time to complete the project is three (3) years, with an
-
Aramco company was awarded a $63 million contract to build a bridge. The estimated time to complete the project is three (3) years, with an estimated cost of $48 million. Assuming that the cost estimates do not change, the project is expected to generate $15 million in profit. The following is a schedule on the project:
2018
2019
2020
Cost incurred (cumulative)
18,000,000
35,000,000
48,000,000
Estimate total cost
48,000,000
48,000,000
48,000,000
Billings
23,000,000
22,000,000
18,000,000
Cash Collected
15,000,000
20,000,000
28,000,000
What is the percentage completed of 2018?
What is the revenue of 2019?
What is the profit recognized in 2020?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started