Question

1 Approved Answer

Arizona Desert Homes (ADH) constructed a new subdivision during 2012 and 2013 under contract with Cactus Development Co. Relevant data are summarized below: Contract Amount

Arizona Desert Homes (ADH) constructed a new subdivision during 2012 and 2013 under contract with Cactus Development Co. Relevant data are summarized below: Contract Amount $3,000,000

Cost: 2012 1,200,000

2013 600,000

Gross Profit: 2012 800,000

2013 400,000

Contract billings: 2012 1,500,000

2013 1,500,000

ADH uses the percentage-of-completion method to recognize revenue.

In its December 31, 2012, balance sheet, ADH would report:

A.

The asset, cost and profits in excess of billings, of $500,000.

B.

The liability, billings in excess of cost, of $300,000.

C.

The asset, contract amount in excess of billings, of $1,500,000.

D.

The asset, deferred profit, of $400,000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applications Of Statistical Sampling To Auditing

Authors: Alvin A. Arens, James K. Loebbecke

1st Edition

0130391565, 978-0130391568

More Books

Students also viewed these Accounting questions

Question

What does it mean that linux is open source

Answered: 1 week ago

Question

Draw a schematic diagram of I.C. engines and name the parts.

Answered: 1 week ago