Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

As a construction manager, you are asked to develop detailed time and cost plans for the construction of a new football stadium, with a gross

As a construction manager, you are asked to develop detailed time and cost plans for the construction of a new football stadium, with a gross floor area of 30,000 m2, in Lincoln City.
Task A: Using the following information and costs from a similar project that you built in 2012 in the South East of England, prepare a detailed cost plan for the proposed stadium in Lincoln in 2022.[10 Marks]
Regional Stadium Cost Model
cost/m2
gross floor area
Substructure
46.46
Frame
113.89
Upper Floors
60.57
Roof
124.14
Stairs
21.32
External walls, windows and doors
45.07
Internal walls and partitions
41.95
Internal doors, wall, floor & ceiling finishes
55.65
Furniture and fittings
32.47
Building Services
243.36
Total construction cost
784.88
MSc Construction Science and Management BTE9005M
The external works are budgeted to cost 1m.
To this sum needs to be added 18% for preliminaries, overheads and a contingency.
From your experience you estimate that costs in the East Midlands of England are 6% cheaper than those in the South East. Adjust your budget accordingly.
Assuming an average inflation rate of 1% per year (from 2012 to 2022), adjust your budget accordingly.
Task B: Develop a programme for the project based upon the following information and criteria. [10 Marks] ID Activity Information and Criteria
1
Mobilisation
3 weeks
2
Substructure
Allow 18 weeks
3
Frame
The steel frame is not available until week 20 and will take 6 weeks to complete
4
Upper Floors
The upper floors are pre-cast concrete which will not be available until week 24. Allow 10 weeks for installation
5
Roof
Roofing work can commence 8 weeks after the upper floors. Allow 4 weeks for completion
6
Stairs
Pre-cast concrete stairs to be installed at the same time as the upper floors
7
External walls, windows and doors
External cladding to proceed 2 weeks after the roof commence. Allow 7 weeks for completion
8
Internal walls and partitions
To commence as soon as the structure is watertight [after activity 7]. Allow 7 weeks
9
Internal doors, wall, floor & ceiling finishes
To commence 4 weeks after the Internal walls and partitions. Allow 9 weeks for completion
10
Furniture and fittings
Fitting out to commence 4 weeks after activity 9 has commenced. Allow 7 weeks
11
Building Services
Building services can commence 3 weeks before the building is watertight. Installation to be completed 4 weeks after activity 9 is completed
12
Builders work in connection
BWIC to be completed as required and as Building Services are installed
13
Commissioning, final clean and handover
Allow 3 weeks for final snagging after the completion of all other works
14
External works
External works to proceed, as weather allows, for completion at the same time as activity 13
MSc Construction Science and Management BTE9005M
Task C:
I.
Use the programme and the cost plan to produce cash flow forecast to give the cost of the project each month. [5 Marks].
i.
Now sum the monthly costs to give the total value of the project each month [5 Marks]
ii.
Now use this data to plot an S curve [5 Marks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting A Business Perspective

Authors: Jefferson Williams, Roger Hermanson, James Don Edwards

10th Edition

1930789793, 978-1930789791

More Books

Students also viewed these Accounting questions

Question

How can an outline help you?

Answered: 1 week ago