As a metallurgist, you are required to sizing hydrocyclones for a ball mill circuit. Target overflow particle size is 8 0 % passing 1 0

As a metallurgist, you are required to sizing hydrocyclones for a ball mill circuit. Target overflow particle size is 80% passing 105\mu m. The pressure drop across the cyclone is 30 kPa. Slurry feed rate is 2,000 m3 h-1. Slurry is 56% by weight of solids with the solid specific gravity of 4.0. Using the Arterburn technique,
a) Select the size of Krebs cyclones.
b) Determine the number of cyclones required to meet the capacity.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Engineering Heat Transfer

Authors: G. F. Nellis, S. A. Klein

1st Edition

110717953X, 9781107179530

More Books

Students also viewed these Chemical Engineering questions

Question

What are the functions of top management?

Answered: 1 week ago

Question

Bring out the limitations of planning.

Answered: 1 week ago

Question

Why should a business be socially responsible?

Answered: 1 week ago

Question

Discuss the general principles of management given by Henri Fayol

Answered: 1 week ago

Question

Does it avoid using personal pronouns (such as I and me)?

Answered: 1 week ago

Question

Does it clearly identify what you have done and accomplished?

Answered: 1 week ago