As a project manager, you are in the process of determining reserve requirements for your project. You want to identify reserves for known risk that
As a project manager, you are in the process of determining reserve requirements for your project. You want to identify reserves for known risk that you have expected in between the project execution. What type of reserve will you identify? A. Contingency B. management C. risk response D. mandatory