As a project manager, you write a communication plan for your new project. You include monthly email check-ins that review a high-level summary of project
As a project manager, you write a communication plan for your new project. You include monthly email check-ins that review a high-level summary of project updates. What group should receive this type of communication? Project managers Whole company Core team members Key stakeholders