Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

As an analysis, you were contracted by Mambo Innovations LTD to advise them on issues relating to its new product development project. Using work breakdown

As an analysis, you were contracted by Mambo Innovations LTD to advise them on issues relating to its new product development project. Using work breakdown methodology, you have identified the project as consisting of coded A,B,C,.......,K. You have also identified eachactivity immediate predecessors and estimated activity times (pessimistic (P), Most likely (M) and optimistic (O)), crash time (CT), normal costs (NC) and crash costs (CC). The dependence table below presents a summary of the resulting data.

TIME COST
Activity Predecessor Optimistic (0) Most likely (M) Pessimistic (P) Crash Normal Crash
A - 4 6 8 3 100 250
B - 1 5 5 3 75 225
C A 3 3 3 1 120 190
D A 4 5 6 3 200 325
E A 1 3 2 1 175 325
F B,C 3 4 5 2 200 450
G B,C 1 4 5 1 250 350
H E,F 5 6 7 3 150 375
I E,F 2 5 8 2 325 425
J D,H 3 4 5 3 225 475
K G,I 3 5 7 2 175 250

a)Determine the expected activity duration (Normal Time) from the three activity time estimates

b)Construct a network diagram for the above project and hence using the activity normal time estimate, determine the project duration (d) and the associated critical path

c)Using the result in (b) above, construct Float Table for the project and interpret

d)Suppose, the firm wishes to complete the project 1 monthearlier than the estimated time, construct the resulting activity schedule (duration and critical activities) and the resulting total cost .

e)Using the result in (D) above and given thatZ=(D - ) / find probabilities that the project duration will be

  1. Between 18 and 26 months
  2. Less than 30
  3. Greater than 27 months

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Partial Differential Equations With Fourier Series And Boundary Value Problems

Authors: Nakhle H Asmar

1st Edition

0486820831, 9780486820835

More Books

Students also viewed these Mathematics questions