Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

As an energy engineer at your company, you find 12 large exhaust fans constantly running to exhaust general plant air (no localized heavy pollution). They

As an energy engineer at your company, you find 12 large exhaust fans constantly running to exhaust general plant air (no localized heavy pollution). They are each powered by 30 kW electric motors with loads of 34 kW each. You find they can be turned off periodically with no adverse effects. You place them on a central timer so that two of them are turned off for 10 minutes each hour. At any time, two of the fans are off, and the other ten fans are running. The fans operate ten h/day, 340 days/year. By using the following costs, answer each question.

* Demand charge: 10 USD/kW/month

* Energy charge: 0.08 USD/kWh

a) What is the annual demand saving in USD?

b) What is the annual energy saving in USD?

c) What is the total saving in USD?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Lakeside Company Case Studies In Auditing

Authors: John Trussel, J. Douglas Frazer

12th Edition

0132567253, 978-0132567251

More Books

Students also viewed these Accounting questions