Question
1 Approved Answer
As following chart is about preceded and followed relationship and cost slope of each processes. Obtain a minumum cost for reducing 4 weeks from total
As following chart is about preceded and followed relationship and cost slope of each processes. Obtain a minumum cost for reducing 4 weeks from total duration with using MCX(Minimum cost expediting) method. please use diagram of ADM.
ACTIVITY Duration (Weeks) 2 3 Possible reduction weeks) Cost Slope (Weeks) A 2 B 4 2 FOLLOWE D BY B, C, D E F G H J I, K I, K L J 90 80 70 90 D 5 3 7 2 4 2 150 4 2 3 1 1 2 E F G H I J K L M N N 4 80 100 120 50 60 100 70 2 2 1 2 2 M M N 4 3 2 NONEStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started