As of Dec. 31, 2019, Trinity Construction is confident that their project #10101 located in Bryan, TX is going to make a loss of $250,000
As of Dec. 31, 2019, Trinity Construction is confident that their project #10101 located in Bryan, TX is going to make a loss of $250,000 when the project is completed in May, 2020 as the total estimated cost for this project has increased to 1,750,000 after a major error on project budget was disclosed. The total estimated cost before this disclosure was $1,350,000. This projects contract amount is $1,500,000 and it started in March 1, 2018. Trinity construction has been using the percentage of completion method in developing their income statement and it reported the gross profit of $52,500 from this project in their 2018 income statement as shown below. As of Dec. 31, 2019, the cumulative percentage of completion of this project is determined to be 70%. Fill out the blank cells in the table.
Yr | Project | Cumulative POC | Revenue | Expenses | Loss Adj. exp. | Gross Profit /loss |
2018 | #10101 | 35% | $525,000 | $472,500 | - | $52,500 |
2019 | #10101 | 70% |
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started