As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows: Task a PDCP b d e f Duration (minutes) 0.2 0.4 0.2 0.4 1.2 1.2 1.0 Immediate Predecessor Click here for the Excel Data File The minimum cycle time PIJE a b d C e, f Do each of the following: a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.) minutes per unit

image text in transcribed

image text in transcribed

Do each of the following: a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.) b. Determine the minimum number of stations needed. (Round your answer to the next whole number.) c. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ignite Your Lyfe Self Esteem Through Entrepreneurship

Authors: Jameelah Wilkerson

1st Edition

979-8458529761

More Books

Students also viewed these General Management questions