Question

1 Approved Answer

As per the project plan, your project will have a very short regression testing phase. Foreseeing a risk, your lead asks you and your team

As per the project plan, your project will have a very short regression testing phase. Foreseeing a risk, your lead asks you and your team to prioritize the test cases as and when you create so that the prioritized test cases can be executed first during regression. Do you think that this prioritization will help in doing regression?
Select one:
a. No, only a schedule extension or increase in resources can help this situation.
b. No, an adhoc or random testing should help this situation better.
c. Yes, the prioritized test suite can better meet the objective than would an ad hoc or random ordering of test cases.
d. Yes, the prioritized test suite would result in a complete fault detection saving cost and time.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Processing Fundamentals Design And Implementation

Authors: David M. Kroenke

5th Edition

B000CSIH5A, 978-0023668814

More Books

Students also viewed these Databases questions