As per the project plan, your project will have a very short regression testing phase. Foreseeing a risk, your lead asks you and your team
As per the project plan, your project will have a very short regression testing phase. Foreseeing a risk, your lead asks you and your team to prioritize the test cases as and when you create so that the prioritized test cases can be executed first during regression. Do you think that this prioritization will help in doing regression?
Select one:
a No only a schedule extension or increase in resources can help this situation.
b No an adhoc or random testing should help this situation better.
c Yes, the prioritized test suite can better meet the objective than would an ad hoc or random ordering of test cases.
d Yes, the prioritized test suite would result in a complete fault detection saving cost and time.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started