As standard time = Set up time + Time per piece No. of pieces produced . Standard time for manufacturing 50 jobs 35+ 8 x
As standard time = Set up time + Time per piece No. of pieces produced . Standard time for manufacturing 50 jobs 35+ 8 x 50 435 min 7 hours and 15 min Standard time x 100 Efficiency of operator Actual time 435 x 100 390 111.5%. ILLUSTRATION 3: Following datas were obtained by a work study. Man from a study conducted by hours. (1) Maintenance time (a) Get out and put away tools 12.0 min/day (b) Cleaning of machine = 5.0 min day (c) Oiling of machine = 5.0 min/day (d) Replenish coolant supply = 3.0 min day (i) Interruption (a) Interruption by foreman = 5.0 min/day (b) Interruption by porter etc. = 4.0 min day (ii) Delay time due to power failure etc. = 6.0 min/day (iv) Personal time = 20.0 min/day Calculate total allowances, total available cycle time productive hours, considering a working day of 8 hours. k14
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started