As the PM, you have completed your power-interest (or impact-influence) grid. One stakeholder has been placed in the high power (influence) & high interest (impact)
As the PM, you have completed your power-interest (or impact-influence) grid. One stakeholder has been placed in the high power (influence) & high interest (impact) box. How will you engage with this stakeholder? Keep informed Manage closely Keep satisfied Monitor only