As the Project manager of a Satellite Uplink project, you have created a Schedule Management plan. You obtain the data shown in the table below

As the Project manager of a Satellite Uplink project, you have created a Schedule Management plan. You obtain the data shown in the table below about three of the many Tasks you need to complete before Project Closure.(duration in days):

If these three tasks (i.e., Tasks A, B, and C) are not part of the critical path of a project, what is the PERT estimate for the duration of the project?

a) 22.5 Days

b) 10.33 Days

c) 32 Days

d) Cannot be determined

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Management Accounting

Authors: Martin G Jagels, Michael M Coltman

8th Edition

0471092223, 9780471092223

More Books

Students also viewed these General Management questions

Question

compare and contrast positivity and negativity;

Answered: 1 week ago

Question

Explain the steps involved in training programmes.

Answered: 1 week ago