ASSIGNMENT 1: REVENUE RECOGNITION INTERMEDIATE ACCOUNTING II (ACC320) SEMESTER II, 2022-2023 Deep Construction Company has a contract to construct a 4,500,000 showroom building for Landslide

ASSIGNMENT 1: REVENUE RECOGNITION INTERMEDIATE ACCOUNTING II (ACC320) SEMESTER II, 2022-2023

Deep Construction Company has a contract to construct a 4,500,000 showroom building for Landslide Incorporation. The contract is to start in July 2020, and the building is to be completed in October 2022. Following are contract costs incurred during the year, estimated costs to complete the contract, billings to and collections from Landslide Incorporation for 2020, 2021, and 2022. 2020 2021 2022 Cost incurred during the year $ 1,000,000 $ 1,916,000 $ 2,360,250 Estimated cost to complete 3,000,000 $ 1,640,250 - Progress billing to date 900,000 3,300,000 4,500,000 Collections to date 750,000 2,500,000 4,300,000

REQUIRED: a) Using percentage-of-completion method, prepare schedules to compute the profit and loss to be recognized as a result of this contract for the year ended October 31, 2020, 2021 and 2022.

b) Using cost recovery method, prepare schedules to compute the profit and loss to be recognized as a result of this contract for the year ended October 31, 2020, 2021 and 2022.

c) Prepare a complete set of journal entries for 2022 (using the percentage-of-completion method).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Draw a picture consisting parts of monocot leaf

Answered: 1 week ago