Assignment 2 - Learning Curve Part 1 : The first unit took 2 4 hours of labor to produce. The company has experienced a 9
Assignment Learning Curve
Part :
The first unit took hours of labor to produce. The company has experienced a learning curve when producing similar designs. The company is interested in estimating the total time and cost to complete the next units. So your job as the production cost estimator is to prepare the estimate. Knowing that hours are available, $ is the available budget for the labor cost and company pays $ per hour for its labor:
Develop a learning curve model to show how time and direct labor costs decrease with learning.
Does the company have adequate time to produce all the units?
Estimate the time and the labor cost it will take to complete the unit.
How much would the company expect to pay as labor costs for all the units?
If the company affords only $ as labor cost? How many units can be produced within the available budget for the labor cost?
What would be the new learning rate, if the company could pay only $ for all the units?
With the new learning rate, how many units can be produced within the available hours? And what would be the total cost of these units? How much will be the remaining budget?
Part :
Even with the new learning rate Q the company is not able to finish the units within the available time hours Therefore, the company is considering the introduction of a subcontractor to produce the remaining units within the remaining budget. The company wants to know whether to select Subcontractor # or # to continue.
tableSubcontractor #Subcontractor #UnitsTime in hours,Units,Time in hours,
The company is concerned in estimating the total time and cost for each subcontractor to complete the remaining units:
Develop a learning curve model for each subcontractor for units.
If company expects to buy and units from Subcontractor #:
a How long it took to produce them?
b What would be your expected cost for the company if Subcontractor # charges $ for each laborhour?
If company expects to buy and company from Subcontractor # :
a How long it took to produce them?
b What would be your expected cost for the company if Subcontractor # charges $ for each laborhour?
Should you encourage Subcontractor or to continue? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started