Question
ASSIGNMENT QUESTION You are required to advise each of the Plaintiff and the Defendant for the two legal disputes that arise from the Background facts
ASSIGNMENT QUESTION
You are required to advise each of the Plaintiff and the Defendant for the two legal disputes
that arise from the "Background facts" below.
The two legal disputes are:
1)
Paul v Jacob's River Wines Pty Ltd
2)
Jacob's River Wines Pty Ltd v Darren.
Background facts
Jacob's River Wines Pty Ltd ("JRW") is company engaged in the production and sale in
Australia of a range of wines. In April 2021, JRW decided to introduce its wines bottled in a
new 300ml aluminium slim bottle that has the appearance and feel of conventional glass wine
bottles. The production of the aluminium bottled wine range was scheduled to start at the
beginning of July 2021 in time for a national launch on 1 September 2021. To achieve this
tight schedule, urgent decisions had to be made about JRW's warehousing and bottling
facilities in the Barossa Valley in South Australia.
Across the road from the JRW production facility was a vacant warehouse belonging to Paul
that had been on the market for sale for almost 2 years. This warehouse was only about half the
size required to meet JRW's forecasted needs. However, JRW decided to try and negotiate a
lease of the warehouse from Paul. During preliminary negotiations in May 2021, JRW
indicated it would take only a 1 year lease of the warehouse but that it would consider taking a
5 year lease if Paul was prepared to build an addition to the warehouse. Although initially
reluctant to do so, Paul eventually agreed to make the addition provided JRW took a 7 year
lease. JRW said that it might consider such a longer lease provided that the addition met its
requirements, and that the expanded warehouse was ready by July 2021.
About the middle of May 2021, a draft agreement to lease document had been drawn up by
Paul's lawyer and was sent to JRW for it to read and approve. JRW made several alterations
to the document and attached a set of plans for building the addition. Paul's lawyer then
incorporated all the alterations into a final agreement to lease document, including the agreed
rental of $100,000 per annum and a lease start date of 1 August 2021. Paul signed the final
agreement to lease document on 30 May 2021, sent it to JRW and then he started construction
of the addition in accordance with the plans provided by JRW. However, JRW did not sign
the document even though it was aware that Paul had started construction.
To enable JRW to bottle its wine range, it required a new bottling machine. On 2 June 2021,
JRW entered into a valid written contract with Darren for JRW to buy a new bottling machine
for this purpose, which JRW made known to Darren. This written contract was signed by both
parties and its express contract terms included the price of $2million for the machine. This
was stated to be payable in two instalments, with $200,000 payable on JRW entering into the
contract and the balance of $1,800,000 payable on delivery and installation of the machine at
JRW's bottling facility in the Barossa Valley.
The express contract terms also included clause 15 that made it a "condition" of the contract
that the bottling machine be installed and fully operational by 1 July 2021. However, in June
2021 it became clear that Darren would be unable to meet the 1 July 2021 deadline, but
through no fault on his part. The bottling machine, which had to be imported from Germany,
arrived in Adelaide in a damaged condition and this damage was discovered only when the
machine was unloaded from its plane transport at the Adelaide airport.Assignment & Instructions - 2021 Tri 2
3
The following are the two legal disputes that have arisen.
1)
Paul v Jacob's River Wines Pty Ltd
In late June 2021, Paul received a letter from JRW stating that it had decided not to proceed
with the lease of his warehouse. JRW's only grounds were, first, that a valid contract had not
been entered into and, secondly, in any event its anticipated requirements for warehouse
facilities had changed and these requirements could now be met by alterations to its existing
warehouse. JRW pointed out clause 5 in the agreement to lease document that states:
"This agreement is subject to Jacob's River Wines Pty Ltd being satisfied, in its
absolute discretion, that on completion of the warehouse addition, the warehouse
meets the company's current and anticipated requirements for such facilities."
No other grounds and arguments were relied on by JRW to not proceed with the lease.
Paul immediately wrote to JRW saying that it could not back out of the lease since he
considered that the agreement to lease document was a valid contract. Furthermore, he had
acted on the agreed terms in constructing the warehouse addition that conformed exactly to the
plans supplied by JRW, and the expanded warehouse would be ready by the 1 August 2021
lease start date.
2)
Jacob's River Wines Pty Ltd v Darren
On 2 July 2021, JRW sent a letter to Darren stating JRW's contract to purchase the bottling
machine was terminated by JRW based on the ground that Darren had breached the express
contract term in clause 15 of the signed written valid contract. Clause 15 states:
"It is a condition of this contract that the bottling machine is installed and fully
operational by 1 July 2021."
In the alternative, JRW stated in its letter that the contract had ended based on the ground that
it had been discharged by frustration. No other grounds and arguments were relied on by
JRW to end the contract.
On receiving JRW's letter, Darren replied disputing that the contract could be terminated or
had ended by frustration. The reply included an offer for Darren to pay all costs of alternative
bottling of the wine until the new machine was fully operational, which would be at the end of
September 2021.
Additional background and assumptions
For the first legal dispute in 1), the fourth to sixth required elements of a valid contract are all
satisfied (and so they do not need to be discussed).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started