Question

1 Approved Answer

(assume 6 min. per vehicle, 15 stations) Concept hourly capacity = 15 stations x 4 vehicles/hour= 60 vehicles per hour that could be tested assuming

(assume 6 min. per vehicle, 15 stations)

Concept hourly capacity = 15 stations x 4 vehicles/hour= 60 vehicles per hour that could be tested assuming no delays.

What would be the daily capacity of the testing site assuming a 10 hour workday = 100

Assume 25 feet per vehicle.

Concept includes 4,000 feet of total queuing (2 lanes @ 2,000 feet each) from entry point at street to testing station.

This allows for ______ vehicles that can queue (_____ feet/ ____ feet per vehicle)

Once filled, the last vehicle in the queue would have an approximate _____ minute wait time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management

Authors: Jay Heizer, Barry Render

10th edition

978-0136119418, 136119417, 978-0132163927

More Books

Students also viewed these General Management questions