Assume a project costs Sh 30,000 and yields the following uncertain cashflows:
Year Cashflow
1 12,000
2 14,000
3 10,000
4 6,000
Assume also that the certainty equivalent coefficients have been estimated as follows:
0 = 1.00
1 = 0.90
2 = 0.70
3 = 0.50
4 = 0.30
The risk-free discount rate is given as 10%
Required
Compute the NPV of the project