Assume a project has the following expected cash flows: Year Expected Net Cash Flow 0 ($400,000) 1 100,000 2 150,000 3 200,000 4 250,000 What
Assume a project has the following expected cash flows:
Year | Expected Net Cash Flow |
0 | ($400,000) |
1 | 100,000 |
2 | 150,000 |
3 | 200,000 |
4 | 250,000 |
What is the projects payback (payback period)?
A | 2.00 years |
B | 2.25 years |
C | 2.50 years |
D | 2.75 years |
E | 3.15 years |