Assume ABC Company contracted to complete a project for a customer for a contract price of $2,000,000. The project began in 2019 and will be

Assume ABC Company contracted to complete a project for a customer for a contract price of $2,000,000. The project began in 2019 and will be completed in 2020. Data related to the project is summarized below:

2019 2020

Construction costs incurred during the year $ 400,000 $ 1,475,000

Construction costs incurred in prior years $ 0 $ 400,000

Cumulative actual construction costs $ 400,000 $ 1,875,000

Estimated costs to complete $ 1,200,000 $ 0

Total Estimated and Actual Construction

Costs $ 1,600,000 $ 1,875,000

Billings during the year $ 380,000 $ 1,620,000

Cash collections during the year $ 250,000 $ 1,750,000

Required:

  1. Compute the amount or Revenue and Gross Profit to be recognized in each year (2019 and 2020) using the percentage of completion method, recognizing income over a period of time.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting

Authors: Pauline Weetman

2nd Edition

0273718452, 978-0273718451

More Books

Students also viewed these Accounting questions

Question

What are the diff erences between groups and teams?

Answered: 1 week ago

Question

If you were Dans friend, what might you say to alter his behaviors?

Answered: 1 week ago