Assume fixed overhead was budgeted at $812,000 when 62,000 machine hours were estimated to be used. Given the following data: Actual units produced: 13,060 Actual

Assume fixed overhead was budgeted at $812,000 when 62,000 machine hours were estimated to be used. Given the following data:

Actual units produced: 13,060

Actual machine hours worked: 63,800

Actual variable overhead incurred: $487,000

Actual fixed overhead incurred: $802,100

Standard variable overhead rate per machine hour: $7.00

Standard production time per unit: 5 hours

the variable overhead efficiency variance is:

  • $10,500U.
  • $10,500F.
  • $12,600U.
  • $12,600F.
  • None of the answers is correct.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Horngrens Financial & Managerial Accounting The Financial Chapters

Authors: Tracie L. Miller Nobles, Brenda L. Mattison, Ella Mae Matsumura

4th Edition

0133255573, 978-0133255577

More Books

Students also viewed these Accounting questions