Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Assume for the following project that the duration of each activity follows a beta probability distribution with parameters a, m and b. Determine the probability

Assume for the following project that the duration of each activity follows a beta probability distribution with parameters a, m and b. Determine the probability that the project will be finished in 21 weeks or less. What must the deadline be set to if we want to have a 99% chance of completing the project on time? (book chapter 6 in Essentials ofManagement Science)

image text in transcribed \begin{tabular}{lcccc} \hline Activity & Immediate predecessors & a & m & b \\ \hline A & & 1 & 2 & 3 \\ B & B & 2 & 3 & 4 \\ C & A, C & 3 & 4 & 6 \\ D & B & 3 & 5 & 8 \\ E & C & 4 & 5 & 6 \\ F & D, F & 5 & 7 & 10 \\ G & E, G & 3 & 4 & 5 \\ H & 1 & 2 & 3 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Managerial Accounting

Authors: Peter Brewer, Ray Garrison, Eric Noreen

7th edition

978-1259675539, 125967553X, 978-1259594168, 1259594165, 78025796, 978-0078025792

Students also viewed these General Management questions

Question

What is a residual plot?

Answered: 1 week ago