Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,760,000. The project began in 2016 and was completed in 2017. Data relating

Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,760,000. The project began in 2016 and was completed in 2017. Data relating to the contract are summarized below:

2016 2017
Costs incurred during the year $ 364,000 $ 2,175,000
Estimated costs to complete as of 12/31 1,456,000 0
Billings during the year 520,000 1,780,000
Cash collections during the year 282,000 1,830,000
Required:

1. Compute the amount of revenue and gross profit or loss to be recognized in 2016 and 2017 assuming Nortel recognizes revenue over time according to percentage of completion. (Enter your answers in million. Use percentages as calculated and rounded in the table below to arrive at your final answer. Losses and expenses should be indicated with a minus sign.)

2016 2017
Estimated total gross profit (loss)
Percentages of completion
Choose numerator

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Auditing E4 Im

Authors: KNAPP

4th Edition

0324048602, 978-0324048605

More Books

Students also viewed these Accounting questions