Assume that a company provided the following cost formulas for three of its expenses (where q refers to the number of hours worked): Rent (fixed)
Assume that a company provided the following cost formulas for three of its expenses (where q refers to the number of hours worked):
Rent (fixed) | $ 3,000 |
---|---|
Supplies (variable) | $ 4.00q |
Utilities (mixed) | $150 + $0.75q |
The companys planned level of activity was 2,000 hours and its actual level of activity was 1,880 hours. The actual amount of supplies expense for the period was $7,800. What is the activity variance for supplies expense?