Question

1 Approved Answer

Assume that a project manager expects to finish a project in 21 days as shown in the table below. However, the owner of the

Assume that a project manager expects to finish a project in 21 days as shown in the table below. However,

Assume that a project manager expects to finish a project in 21 days as shown in the table below. However, the owner of the project wants it in 14 days and any period after 14 days the project manager has to pay penalty cost of $100 per day. Indirect project .costs $250 per day Immediate Crash Cost (predecessor(s ($) 1200 2000 900 2000 A, B B Project Activity and Cost Data C, D E E G 1200 1400 Crash Time Normal Cost Normal Time ((days ($) ((days 1000 800 600 1500 900 4 3 1 2 3 1 3 3 5 5 2 3 900 1300 F 900 G 900 500 H ?How much is the total penalty costs if the manager could not crash 5 2 3 5 Activity A B C D E LL : $700 a O $1750 b O $2100 .CO $1400 .d O

Step by Step Solution

3.42 Rating (165 Votes )

There are 3 Steps involved in it

Step: 1

The image contains a table with project activity and cost data and a question about calculating the ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these General Management questions

Question

What is the effect of word war second?

Answered: 1 week ago