Assume that ABC Co. calls you as an expert in feasibility study to prepare a feasibility study for a project, using the following data: This
Assume that ABC Co. calls you as an expert in feasibility study to prepare a feasibility study for a project, using the following data:
- This project needs 2 years for establishment and will operate 5 years.
- The required land 6000 meter with LE 1000 per meter (in the first year).
- The cost of buildings LE 15 million, 60% will be paid in the first year and 40% in the second year.
- The equipment include local equipment costs LE 4 million, foreign equipment costs $ 2 million. They will be bought in the second year.
- The furniture and office equipment cost LE 3 million, in the second year.
- The cost of transportation means LE 1 million, in the second year.
- The organization cost (Feasibility study and other costs) LE 3 million (2 million in the first year, the rest in the second year).
- The first working capital LE 2 million, in the second year.
- The project will be financed from the owners and the bank; the bank will grant LE 10 million longterm loans (in the beginning of the second year) with interest rate 10% annually, the loan will be paid during the operating period.
- The emergency reserve for the increase in the tangible fixed assets prices will be 10% of the cost of fixed assets.
- The exchange rate is LE 5.5 for $ 1
Required: Prepare a schedule for the investment costs of the proposed project distributed over the establishment years.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started